Rate and regulatory matters and related litigation
Williams' interstate pipeline subsidiaries, including Williams Pipe Line, have various regulatory proceedings pending. As a result of rulings in certain of these proceedings, a portion of the revenues of these subsidiaries has been collected subject to refund. As to Williams Pipe Line, revenues collected subject to refund were $179 million at December 31, 1995; it is not expected that the amount of any refunds ordered would be significant. Accordingly, no portion of these revenues has been reserved for refund. As to the other pipelines, see Note 12 for the amount of revenues reserved for potential refund as of December 31, 1995.
In 1992, the FERC issued Order 636, Order 636-A and Order 636-B. These orders, which have been challenged in various respects by various parties in proceedings pending in the U.S. Court of Appeals for the D.C. Circuit, require interstate gas pipeline companies to change the manner in which they provide services. Williams Natural Gas implemented its restructuring on October 1, 1993, and Northwest Pipeline, Texas Gas and Transcontinental Gas Pipe Line implemented their restructurings on November 1, 1993. Certain aspects of each pipeline company's restructuring are under appeal.
Contract reformations and gas purchase deficiencies
Each of the natural gas pipeline subsidiaries has undertaken the reformation of its respective gas supply contracts. None of the pipelines has any significant pending supplier take-or-pay, ratable take or minimum take claims.
In 1994, Williams Natural Gas and a producer executed a number of agreements to resolve outstanding issues. Portions of the settlement were subject to regulatory approvals, including the regulatory abandonment of a certain Williams Natural Gas gathering system on terms acceptable to Williams Natural Gas. On May 2, 1995, the FERC issued orders granting the requisite approvals; however, one party has requested rehearing of the decision regarding abandonment of the gathering system.
Current FERC policy associated with Orders 436 and 500 requires interstate gas pipelines to absorb some of the cost of reforming gas supply contracts before allowing any recovery through direct bill or surcharges to transportation as well as sales commodity rates. Under Orders 636, 636-A and 636-B, costs incurred to comply with these rules are permitted to be recovered in full, although 10 percent of such costs must be allocated to interruptible transportation service.
The FERC initially approved a method for Northwest Pipeline to direct bill its contract-reformation costs, but when challenged on appeal, sought a remand to reassess such method. Northwest Pipeline has received an order from the FERC that requires a different allocation of such costs and has rebilled its customers accordingly. While certain customers continue to challenge the FERC methodology, Northwest Pipeline does not expect the reallocation or the challenge to result in a significant financial impact upon the company.
Pursuant to a stipulation and agreement approved by the FERC, Williams Natural Gas has made three filings to direct bill take-or-pay and gas supply realignment costs. The first provided for the offset of certain amounts collected subject to refund against previous take-or-pay direct-billed amounts and, in addition, covered $24 million in new costs. This filing was approved, and the final direct-billed amount, taking into consideration the offset, was $15 million. The second filing covered $18 million in additional costs, and provided for an offset of $3 million. The third filing covered additional costs of $8 million which are similar in nature to the costs in the second filing. An intervenor has filed a protest seeking to have the Commission review the prudence of certain of the costs covered by the second and third filings. Williams Natural Gas believes that the second and third filings will most likely be approved. As of December 31, 1995, this subsidiary had an accrual of $87 million for its then estimated remaining contract-reformation and gas supply realignment costs. This accrual was increased in December 1995 as a result of a ruling by the U.S. Court of Appeals for the Tenth Circuit regarding the terms of certain contracts with producers. Williams Natural Gas will make additional filings under the applicable FERC orders to recover such further costs as may be incurred in the future. Williams Natural Gas has recorded a regulatory asset of approximately $84 million for estimated future recovery of the foregoing costs.
On September 18, 1995, Texas Gas received FERC approval of a settlement regarding Texas Gas' recovery of gas supply realignment costs. The settlement provides that Texas Gas will recover 100 percent of such costs up to $50 million, will share in costs incurred between $50 million and $80 million, and will absorb any such costs above $80 million. The settlement also extends Texas Gas' pricing differential mechanism to November 1, 1996, and beyond that date for contracts in litigation as of that date. Through December 31, 1995, Texas Gas has paid approximately $53 million for gas supply realignment costs, primarily as a result of contract terminations, and has accrued a liability of approximately $27 million for its estimated remaining gas supply realignment costs. Texas Gas has recovered approximately $44 million in gas supply realignment costs, and in accordance with the terms of its settlement has recorded a regulatory asset of approximately $23 million for the estimated future recovery of such costs, which will be collected from customers over the next two years. Ninety percent of the cost recovery is collected through demand surcharges on Texas Gas' firm transportation rates; the remaining 10 percent is recoverable from interruptible transportation service.
In 1983, the FERC issued Order 94-A, which permitted producers to collect certain production related costs from pipelines on a retroactive basis. Pursuant to FERC orders, Texas Gas and Transcontinental Gas Pipe Line direct billed their customers for such costs paid to producers. In 1990, the U.S. Court of Appeals for the D.C. Circuit overturned the FERC's orders authorizing direct billing for such costs. In December 1995, Texas Gas entered into a settlement by which it resolved its final refund obligations as to these costs. Transcontinental Gas Pipe Line has resolved its refund obligations except for an amount of approximately $7 million. Transcontinental Gas Pipe Line has refunded that amount, reserving the right to recover the amount paid if the ruling is reversed on appeal.
The foregoing accruals are in accordance with Williams' accounting policies regarding the establishment of such accruals which take into consideration estimated total exposure, as discounted and risk-weighted, as well as costs and other risks associated with the difference between the time costs are incurred and the time such costs are recovered from customers. The estimated portion of such costs recoverable from customers is deferred or recorded as a regulatory asset based on an estimate of expected recovery of the amounts allowed by FERC policy. While Williams believes that these accruals are adequate and the associated regulatory assets are appropriate, costs actually incurred and amounts actually recovered from customers will depend upon the outcome of various court and FERC proceedings, the success of settlement negotiations and various other factors, not all of which are presently foreseeable.
Since 1989, Texas Gas and Transcontinental Gas Pipe Line have had studies under way to test certain of their facilities for the presence of toxic and hazardous substances to determine to what extent, if any, remediation may be necessary. Trans continental Gas Pipe Line has responded to data requests regarding such potential contamination of certain of its sites. The costs of any such remediation will depend upon the scope of the remediation. At December 31, 1995, these subsidiaries had reserves totaling approximately $45 million for these costs.
Certain Williams subsidiaries, including Texas Gas and Transcontinental Gas Pipe Line, have been identified as potentially responsible parties (PRP) at various Superfund and state waste disposal sites. Although no assurances can be given, Williams does not believe that the PRP status of these subsidiaries will have a material adverse effect on its financial position, results of operations or net cash flows.
In February 1995, Transcontinental Gas Pipe Line was served as a defendant in a lawsuit filed in U.S. District Court in Virginia by three individuals for alleged violations of several provisions of both federal and state laws. Since 1991, Transcontinental Gas Pipe Line has worked with the appropriate Virginia authorities to resolve certain emissions issues also raised by the individuals. On October 13, 1995, the court dismissed the lawsuit but provided that the plaintiffs could amend and refile their complaint to allege a state law nuisance claim and they have done so. Transcontinental Gas Pipe Line believes the amended complaint is without merit and is prepared to vigorously defend the suit.
Transcontinental Gas Pipe Line, Texas Gas and Williams Natural Gas have identified polychlorinated biphenyl (PCB) contamination in air compressor systems, soils and related properties at certain compressor station sites. Transcontinental Gas Pipe Line, Texas Gas and Williams Natural Gas have also been involved in negotiations with the U.S. Environmental Protection Agency (EPA) and state agencies to develop screening, sampling and cleanup programs. In addition, negotiations concerning investigative and remedial actions relative to potential mercury contamination at certain gas metering sites have commenced with certain environmental authorities by Williams Natural Gas and Transcontinental Gas Pipe Line. As of December 31, 1995, Williams Natural Gas had recorded a liability for approximately $26 million, representing the current estimate of future environmental cleanup costs to be incurred over the next six to ten years. Texas Gas and Transcontinental Gas Pipe Line likewise had recorded liabilities for these costs which are included in the $45 million reserve mentioned above. Actual costs incurred will depend on the actual number of contaminated sites identified, the actual amount and extent of contamination discovered, the final cleanup standards mandated by the EPA and other governmental authorities and other factors. Texas Gas, Transcontinental Gas Pipe Line and Williams Natural Gas have deferred these costs pending recovery as incurred through future rates and other means.
In connection with the 1987 sale of the assets of Agrico Chemical Company, Williams agreed to indemnify the purchaser for environmental cleanup costs resulting from certain conditions at specified locations, to the extent such costs exceed a specified amount. It appears probable that such costs will exceed this amount. At December 31, 1995, Williams had approximately $7 million accrued for such excess costs. The actual costs incurred will depend on the actual amount and extent of contamination discovered, the final cleanup standards mandated by the EPA or other governmental authorities, and other factors.
A lawsuit was filed on May 14, 1993, in a state court in Colorado in which certain claims have been made against various defendants, including Northwest Pipeline, contending that gas exploration and development activities in portions of the San Juan Basin have caused air, water and other contamination. The plaintiffs in the case sought certification of a plaintiff class. On June 28, 1994, the lawsuit was dismissed for failure to join an indispensable party over which the state court had no jurisdiction. This decision is being appealed by the plaintiffs. Since June 28, 1994, eight individual lawsuits have been filed against Northwest Pipeline in U.S. District Court in Colorado, making essentially the same claims. Northwest Pipeline is vigorously defending these lawsuits.
On December 31, 1991, the Southern Ute Indian Tribe (the Tribe) filed a lawsuit against Williams Production Company, a wholly owned subsidiary of Williams, and other gas producers in the San Juan Basin area, alleging that certain coal strata were reserved by the United States for the benefit of the Tribe and that the extraction of coal-seam gas from the coal strata was wrongful. The Tribe seeks compensation for the value of the coal-seam gas. The Tribe also seeks an order transferring to the Tribe ownership of all of the defendants' equipment and facilities utilized in the extraction of the coal-seam gas. On September 13, 1994, the court granted summary judgment in favor of the defendants. The Tribe lodged an interlocutory appeal with the U.S. Court of Appeals for the Tenth Circuit. Williams Production agreed to indemnify the Williams Coal Seam Gas Royalty Trust (Trust) against any losses that may arise in respect of certain properties subject to the lawsuit. In addition, if the Tribe is successful in showing that Williams Production has no rights in the coal-seam gas, Williams Production has agreed to pay to the Trust for distribution to then-current unitholders, an amount representing a return of a portion of the original purchase price paid for the units. While Williams believes that such a payment is not probable, it has reserved a portion of the proceeds from the sale of the units in the Trust.
In October 1990, Dakota Gasification Company (Dakota), the owner of the Great Plains Coal Gasification Plant (Plant), filed suit in the U.S. District Court in North Dakota against Transcontinental Gas Pipe Line and three other pipeline companies alleging that the pipeline companies had not complied with their respective obligations under certain gas purchase and gas transportation contracts. On September 8, 1992, Dakota and the Department of Justice on behalf of the Department of Energy filed an amended complaint adding as defendants in the suit, Transco Energy Company, Transco Coal Gas Company (Transco Energy Company and Transco Coal Gas Company being wholly owned subsidiaries of Williams) and all of the other partners in the partnership that originally constructed the Plant and each of the parent companies of these entities. Dakota and the Department of Justice sought declaratory and injunctive relief and the recovery of damages, alleging that the four pipeline defendants underpaid for gas, collectively, as of June 30, 1992, by more than $232 million plus interest and for additional damages for transportation services and costs and expenses including attorneys' fees. On March 30, 1994, the parties executed definitive agreements which would settle the litigation subject to final non-appealable regulatory approvals. The settlement is also subject to a FERC ruling that Transcontinental Gas Pipe Line's existing authority to recover in rates certain costs related to the purchase and transportation of gas produced by Dakota will pertain to gas purchase and transportation costs Transcontinental Gas Pipe Line will pay Dakota under the terms of the settlement. On October 18, 1994, the FERC issued an order consolidating Transcontinental Gas Pipe Line's petition for approval of the settlement with similar petitions pending relative to two of the other three pipeline companies (the third pipeline having entered into a settlement) and setting the matter for hearing before an administrative law judge. On December 29, 1995, the administrative law judge issued an initial decision in which he concluded that the settlement was imprudent. If the decision is upheld on appeal, Transcontinental Gas Pipe Line and the other two pipelines would be required to refund to their customers amounts collected in excess of the amounts deemed appropriate by the administrative law judge. The pipelines would be entitled to collect the amount of any such customer refunds from Dakota. The administrative law judge's decision will be appealed; however, in the event that the necessary regulatory approvals are not ultimately obtained and Dakota elects to continue the litigation, Transcontinental Gas Pipe Line, Transco Energy Company and Transco Coal Gas Company intend to vigorously defend the suit.
In connection with agreements to resolve take-or-pay and other contract claims and to amend gas purchase contracts, Transcontinental Gas Pipe Line and Texas Gas each entered into certain settlements with producers which may require the indemnification of certain claims for additional royalties which the producers may be required to pay as a result of such settlements. As a result of such settlements, Transcontinental Gas Pipe Line and Texas Gas have been named as defendants in, respectively, six and two lawsuits in which damages claimed aggregate in excess of $133 million. Texas Gas has settled its two lawsuits for a total cost of $3.7 million, all but $700,000 of which is recoverable as transition costs under Order 636. On July 17, 1995, a judge in a Texas state court granted a motion by Transcontinental Gas Pipe Line for partial summary judgment, rejecting a major portion of the plaintiff's claims in one of its lawsuits. Producers may receive other demands which could result in additional claims. Indemnification for royalties will depend on, among other things, the specific lease provisions between the producer and the lessor and the terms of the settlement between the producer and either Transcontinental Gas Pipe Line or Texas Gas. Texas Gas may file to recover 75 percent of any such additional amounts it may be required to pay pursuant to indemnities for royalties under the provisions of Order 528.
On November 14, 1994, Continental Energy Associates Limited Partnership (the Partnership) filed a voluntary petition under Chapter 11 of the Bankruptcy Code with the U.S. Bankruptcy Court, Middle District of Pennsylvania. The Partnership owns a cogeneration facility in Hazleton, Pennsylvania (the Facility). Hazleton Fuel Management Company (HFMC), a subsidiary of Transco Energy, supplies natural gas and fuel oil to the Facility. As of December 31, 1995, it had current outstanding receivables from the Partnership of approximately $20 million, all of which has been reserved. The construction of the Facility was funded by several banks that have a security interest in all of the Partnership's assets. HFMC has asserted to the Bankruptcy Court that payment of its receivables is superior to the lien of the banks and intends to vigorously pursue the collection of such amounts. HFMC has also filed suit against the lead bank with respect to this and other matters, including the alleged tortious interference with HFMC's contractual relations with the Partnership and other parties. On March 21, 1995, the Bankruptcy Court approved the rejection of the gas supply contract between the Partnership and HFMC. HFMC has in turn asserted force majeure under a contract with a producer under which HFMC purchased natural gas for the Facility.
In addition to the foregoing, various other proceedings are pending against Williams or its subsidiaries incidental to their operations.
While no assurances may be given, Williams does not believe that the ultimate resolution of the foregoing matters, taken as a whole and after consideration of amounts accrued, insurance coverage, recovery from customers or other indemnification arrangements, will have a materially adverse effect upon Williams' future financial position, results of operations and cash flow requirements.
|
|